An ordinary morning in a yacht yard, aboard a yacht under construction. A carpenter arrives on board but cannot start work because the compartment he needs to access is unavailable: an unexpected problem has required further work on the electrical panel. The task is postponed, subsequent work must be rescheduled and everyone involved needs to be informed. The gap between the production schedule and what actually happens during the construction of a yacht reveals the complexity of running a yard.

Daino was created to address precisely that gap. Its developers call it the “brain of the yard”: a digital ecosystem that gathers information, makes it consistent and uses a mathematical engine to propose a better way of organising activities. Artificial intelligence allows users to query it in natural language, while desktop and smartphone applications connect planners with people working on board.

Developed through discussions with Amer Yachts, the project addresses a central challenge for Italian yacht building: introducing industrial planning tools into a production process where manual skills, customisation and responsiveness to owners’ requests remain essential. One point needs to be clear: at the time of the interview, deployment at the yard was imminent and Daino’s benefits had yet to be measured. We discussed the project with engineer and founding partner Giulio Maria Santonico.

Paolo Pascarelli and Giulio Maria Santonico

PressMare - What need led to Daino, and what do you mean by the “brain of the yard”?

Giulio Maria Santonico - It arose from the need to bring together, as far as possible in a craft-based environment, the yard’s information and accumulated knowledge. We wanted a system that people could consult, capable of answering questions about what is happening in production and suggesting how to organise it. That is what we mean by the “brain”: it connects the yard’s knowledge with operational decisions.

PM - Yacht building depends on a delicate balance between industry and craftsmanship. Where do you fit in?

GMS - We want to introduce optimisation and automation of organisational processes into a craft-based system, preserving what makes Italian products distinctive. It starts with people: craftspeople mainly work with their hands and may have limited familiarity with computers. Technology must help the yard and respect its skills; imposing difficult procedures would slow adoption.

PM - You have also studied industrial operations far removed from this model, where automation is taken to the highest level…

GMS - We spent a month visiting plants and speaking with engineers from major automotive groups, including BYD and Geely. They showed us a factory described as 95% automated, with human involvement focused on inspection and quality control. It helped us understand how far industrialisation can go. However, our impression is that taking it to the extreme can diminish the perceived quality of certain finishes, such as stitching and leatherwork: that is an assessment based on what we observed. For Italian yacht building, we believe the aim should be to adopt the best industrial planning tools while retaining the product’s handcrafted identity.

PM - How is the platform structured?

GMS - There are three layers: data collection and standardisation, an optimisation engine, and a simple interface for users. The information covers four areas: production, materials, communication and financial management. They need to interact because a change in production affects purchasing, the people involved and costs.

PM - Does a yard have to replace all the tools it already uses?

GMS - No. Our aim is to connect as closely as possible to the existing digital infrastructure. We do not want to impose a single data-entry system on people with different needs: craftspeople, new workers, yacht project supervisors and office staff. We start with the information already available and build a unified data layer. Making information consistent already improves work, because coherent data can be transferred and communicated faster. Solutions for this stage are already widely used in the sector; the added value comes with the next layer, optimisation.

PM - At what stage of a project does Daino become involved? Can it also be used for refits?

GMS - From day zero, meaning the moment the project enters the system. For a new build, it follows the production plan from the outset; for a refit, the programme of work on the existing vessel is entered. The system adapts to the context and the vessel’s characteristics, including the different requirements of GRP and metal construction.

PM - What underpins the optimisation engine?

GMS - Operations research, the mathematical discipline concerned with optimising industrial systems. We come from management engineering at Sapienza University and have been working on the engine for around three years, alongside our studies and in dialogue with the university. Once the information has been unified, the engine analyses how activities are organised and resources are used, identifying sequences and allocations that reduce downtime and interference between tasks while taking the yard’s constraints into account.

PM - You have mentioned time savings of 20-30% and cost reductions of 5-10%, reaching 15% in some cases. How should those figures be understood?

GMS - They refer to applications of operations research in shipping, not to results achieved by the Daino engine. In that context, systems of this kind have reduced overall work times by 20%, with peaks of 30%, and costs by an average of 5-10%, reaching 15% in some cases. The comparison concerns the method and its potential. We do not yet have measured results with Amer Yachts: we have completed the design and development of the brain, deployment is expected shortly, and the benefits will have to be verified in practice.

PM - Where do savings arise in day-to-day work?

GMS - Take a contractor arriving to work in a compartment and finding it unavailable because of a problem that occurred the previous day. The craftsperson has to return another time, and that day becomes a loss for the project. A system that immediately communicates the unexpected issue and recalculates the schedule coordinates the resources involved more effectively. Savings come from reducing these waiting periods and reorganising activities according to what is actually happening on board.

PM - How is an unexpected issue reported, and what effect does it have on procurement?

GMS - The yacht project supervisor describes it in natural language, for example by writing that painting a compartment has been delayed by six days. The system updates the schedule and related activities, and can also reschedule the ordering or arrival of materials: if the paint will be needed later, there is no point keeping it in storage for a week. Material requirements are therefore linked to the actual schedule, and the same information reaches the purchasing department and the craftspeople due to work after painting.

PM - How far does material traceability extend? Could it lead to a digital passport for the vessel?

GMS - The aim is to track materials throughout their journey: ordering, arrival at the yard, installation on board and any installation problems. This record also makes it possible to assess supplier reliability. Knowing which components have actually been installed then allows a digital passport to be created: together with the yard, we define the checks to be performed after a certain period and link automatic reminders to their due dates. Construction traceability becomes the basis for scheduled maintenance.

PM - Why do you place so much emphasis on internal communication? What tools do users have?

GMS - Because optimising a schedule achieves little if information does not reach the people carrying it out in time. Distributing updates to everyone involved before and after a task accounts for a significant part of planning work. When a task changes, the yacht project supervisor, the next craftsperson and the purchasing department all need to know: the platform centralises these exchanges. We envisage a desktop application for decision-makers and planners, meaning yard managers and yacht project supervisors, and a simpler mobile application for people working on board. It allows them to report unexpected issues, attach photos and provide progress updates. People aboard the vessel become points for gathering and sharing information, making progress reporting more accurate and timely.

PM - What is the role of artificial intelligence in relation to the mathematical engine?

GMS - It is the bridge between the decision-maker and the engine. Interacting directly with an optimisation system would be complex; natural language makes that interaction accessible. Users can describe a problem in words, ask who is working in the owner’s cabin today, consult project data and obtain reports. We therefore assign artificial intelligence a connecting role: making the system’s information and computing capabilities usable by decision-makers.

PM - Can Daino also suggest how to solve a problem?

GMS - It is designed to learn from experience. When it recognises a problem similar to one encountered before, it retrieves the previous report and the solution adopted, assessing the alternatives in the new context. Then there is the overall picture: an unexpected issue in the saloon could be managed by moving or reversing the order of tasks in another area, such as the owner’s cabin. The activities may appear unrelated, but they share people and resources. By analysing these relationships, the engine can identify a reorganisation that, where conditions allow, avoids affecting the delivery date.

PM - Does the benefit differ between custom building and series production?

GMS - The type of problem changes. In custom building, managing changes is particularly important: an owner may change their mind during construction, for example requesting grey marble when white marble has already been purchased. Responding to these requests is a feature of Italian yacht building, and Daino aims to make them easier to manage by recalculating their consequences for the organisation of work. In series production, the challenge is sharing resources between several vessels: workers, machinery, materials and spaces need to be allocated without creating conflicts. Two teams cannot always work in the same compartment at the same time. Optimisation brings benefits in both cases, but in different areas. The decisive distinction is the production model and its constraints rather than the hull material.

PM - How important is the yard’s willingness to rethink the way it works?

GMS - Very important. At Amer Yachts, we found a partner open to innovation: Barbara Amerio expressed a willingness to test existing processes and see whether they could be improved. Working in a certain way for many years does not mean the best solution has been found. A strong craft tradition can come with a tendency to repeat established procedures, so introducing a system like ours also requires a discussion about working methods. Our aim is to make the organisation in which those skills are applied more effective.

PM - Who is behind Daino, and what is your relationship with the university?

GMS - We are an independent company, not a spin-off. We are management engineers trained at Sapienza University and developed the system alongside our studies, starting from our optimisation courses. The team also includes software engineers from Politecnico di Milano, and we are supported by PhD students specialising in optimisation at Sapienza.

PM - In which direction do you want to develop the project?

GMS - We want to bring this ecosystem into yacht building, with a tool that connects knowledge, planning and operational activities. The common thread is making complexity easier to manage: accessible information, coordinated resources and the ability to respond to changes. We believe optimisation can help yards make the most of their expertise and support the flexibility that characterises Italian yacht construction.